Nine buoys, and the end of anchoring at will

Works are under way in Monaco Bay on an organised mooring area of nine deep-water buoys for vessels up to 90 metres. From the summer of 2027, anchoring anywhere else in Monegasque waters will be prohibited.

Nine buoys, and the end of anchoring at will
Photograph by Charles Jacques, via Wikimedia Commons (CC BY-SA 2.0)
Yachts berthed in Port Hercule below the Yacht Club de Monaco. The fleet that fills the harbour each season also anchors in the bay beyond it, and it is that anchorage the Government is now organising.

The works began on 7 October, in water between 45 and 80 metres deep. In Monaco Bay, on the stretch of sea where large yachts have always anchored for the summer and for the principality's major events, the Prince's Government is building an organised mooring area: nine fixed mooring buoys that will replace the season-by-season dropping of anchors with permanent points a vessel can tie to and leave behind.

The reasoning is environmental first and practical second. The Government says repeated anchoring over successive seasons places significant pressure on the seabed, and that fixed mooring points protect the bay's marine environment better than anchors do. The same project, it says, improves navigational safety in busy waters and raises the quality of what the principality offers visiting vessels. The Department of Maritime Affairs has led the project for several years.

Large yachts at anchor in Monaco Bay off Larvotto, with Larvotto Beach at left and the Grimaldi Forum below. The Government has chosen the bay's traditional summer anchorage as the site of the organised mooring area.
Photograph by Laslovarga, via Wikimedia Commons (CC BY-SA 3.0)
Large yachts at anchor in Monaco Bay off Larvotto, with Larvotto Beach at left and the Grimaldi Forum below. The Government has chosen the bay's traditional summer anchorage as the site of the organised mooring area.

The nine buoys will be held by eco-designed anchor blocks and divided by size: four for vessels up to 50 metres, three for vessels up to 70 metres, and two for vessels up to 90 metres. Organised mooring areas exist elsewhere in the Mediterranean, in France and Italy among others, but the Government notes that Monaco's is unusual for its depth, which makes the engineering more complex. Because of where the area sits, it was developed in close consultation with the French maritime authorities.

9
Mooring buoys
up to 90 m
Largest vessels
45 to 80 m
Depth of the site
7 October 2026
Works began
31 March 2027
Completion, no later than
Summer 2027
Operational

Riviera Radio, reporting on the works on Tuesday, added detail that the Government release does not carry. It reported that the installation is being carried out by the Monaco-based company Trasomar in partnership with the French start-up LineUp Ocean, and that the project includes six artificial reef modules made with 3D-printing technology and materials incorporating recycled oyster shells. The modules, it reported, are designed as habitat for marine species including spiny lobsters and filter-feeding organisms, providing about 18 cubic metres of habitat space on 130 square metres of seabed, and the station framed the purpose of the fixed moorings as protecting the bay's Posidonia seagrass beds from dragging anchors.

The Anorep I, a two-seater submersible on display at the Oceanographic Museum. The seabed the new moorings are meant to spare has long been a subject of Monegasque marine research.
Photograph by Dennis G. Jarvis, via Wikimedia Commons (CC BY-SA 2.0)
The Anorep I, a two-seater submersible on display at the Oceanographic Museum. The seabed the new moorings are meant to spare has long been a subject of Monegasque marine research.

The change that matters most arrives with the 2027 summer season, when the area becomes operational. From then on, no vessel will be permitted to anchor anywhere else in waters under Monegasque sovereignty, at any time of year, and the total number of moorings in those waters will fall. Special arrangements may still be made during major maritime events. The Société d'Exploitation des Ports de Monaco will manage the area. While the works run, all other maritime activities are prohibited inside the construction zone for safety reasons, with temporary arrangements promised so that major events can go ahead.

The Government expects the works to last about three and a half months and to be completed no later than 31 March 2027. What is being rationed here is familiar. On land, Monaco manages scarcity by the square metre; the mooring area applies the same logic to the sea. Nine buoys is a small number, and that is the point: the bay's anchorage, long treated as open water, becomes an allocated resource, with the seabed underneath it treated as something the principality intends to keep.

Filed under: Economy

Corrections
None to date. The Chronicle corrects errors promptly and transparently. Read our corrections policy.
Monaco Chronicle
Monaco Chronicle
Read nextA choice of boards, offered a year after the overhaul
Monaco ChronicleEconomy